St Swithins, London
CAT A & B fit out
Design and build
- Design of mechanical services to the 1st floor
- Validation to the existing systems
- Supply and installation of all new Daikin VRF heat recovery systems throughout the project areas
- New control systems to serve the new VRF systems across the floor
- Supply and installation of all new fan coil units to replace the existing across the floor
- All new secondary ductwork, cut to size to meet the design criteria, to serve all the new fan coil units
- Installation of duct-mounted volume control dampers
- A new extract system to serve the new dedicated staff tea point
- Grilles and diffusers, sized to meet the design criteria, with consideration to the maximum noise criteria
- Re-commissioning of the entire air supply / extract systems and the secondary air from each fan coil unit
- Local modifications of the existing drainage pipework to allow connection with the new sanitaryware and tea point / kitchen outlets
- Chlorination and certification of the new staff tea point domestic services
- Amendment of the existing domestic water pipework and drainage pipework to serve the new kitchenette area
- Insulation to all the domestic hot water pipework
- Supply and installation of a waste pump
- Testing, treatment and chlorination
- Certification and client training on completion